The Sprint Burndown Chart displays the remaining effort for a given period of time.
Work remaining is the Y axis and working days is the X axis. When the x and y axis coincide,
the work is complete.
When tracking product development using the Burndown Chart, teams can use a Sprint Burndown Chart
and a Release Burndown Chart.
The Sprint Burndown Chart consists of the following data elements:
Product Backlog Item (PBI)
Task
Name
Status (To Do, In-Progress, Closed)
Original Estimate of time
An array of 10 days by which work effort each day will reduce the time remaining
Sprint Review.
Data Grid:
The data grid is constructed as a table, which means whenever you update the table by
adding or deleting rows or columns or simply changing values in the table, the graph is automatically
updated.
Formulas:
Formulas are embedded in the chart to calculate:
Time remaining each day after each previous work effort.
Total work accomplished for each day.
Scroll down to the Agile Sprint Burndown Chart example below.